From 1 June 2026, net-metering and open-access solar projects commissioned on or after that date must use solar modules listed on MNRE ALMM List-I and solar cells listed on ALMM List-II. MNRE did not grant a blanket extension, but case-by-case relief was allowed for projects with substantial pre-deadline progress, claimed through the National Institute of Solar Energy portal with documentary proof.
Quick Summary Box
What it is
The MNRE Approved List of Models and Manufacturers rule that extended domestic sourcing requirements from solar modules to solar cells for covered projects from 1 June 2026.
Who it is for
anyone commissioning a net-metering or open-access solar project in India during or after mid-2026
Main benefit
It closes the loophole where imported cells were assembled into locally branded modules, which protects subsidy claims, warranty quality and long-term performance.
Key risk
Off-list modules or cells can fail DISCOM inspection and forfeit subsidy eligibility, and a model delisted mid-installation can leave the buyer absorbing the loss.
Typical cost
Reports through 2026 indicated domestic module prices had moved to roughly Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt as the domestic cell rule tightened. Analysts estimated solar tariffs could rise by about 40 to 50 paise per unit in the near term until local cell capacity scaled up.
Best next step
Before paying any advance, ask your vendor for the module List-I registration and the cell List-II registration for the exact models quoted, and verify both on the current MNRE list.
Introduction
For years, India required solar modules to come from approved domestic manufacturers, but the cells inside those modules could be imported. Vendors could assemble imported cells here and still sell the panel under a domestic brand.
ALMM List-II closed that gap for covered projects. From 1 June 2026, the cells inside qualifying modules must also come from approved domestic makers. The rule is short, but it changes quotes, timelines and risk for anyone installing rooftop solar.
Table of Contents
Main Content
How ALMM List-II solar cell rule Works in India
ALMM List-II solar cell rule should be decided from your real Indian site conditions, not from a brochure number. The practical answer depends on tariff, approval, wiring or roof condition, equipment warranty and how you will use the system month after month.
For homeowners, housing societies, EPC vendors and commercial solar buyers, the useful approach is to convert the topic into a short checklist: what is being installed or compared, who approves it, what it costs, how it is metered or warranted, and what happens if something fails.
- ALMM List-I covers solar modules and had already applied to many government-linked schemes.
- ALMM List-II covers solar cells and became mandatory for applicable projects from 1 June 2026.
- Covered categories include net-metering projects and open-access renewable energy projects commissioned on or after 1 June 2026.
- MNRE did not grant a blanket extension, though case-by-case relief was available with documentary proof.
- Relief claims were routed through the National Institute of Solar Energy portal, with a submission window closing 30 June 2026.
- Domestic module prices rose in 2026, with trade reports citing roughly Rs 25 to Rs 27 per watt against an earlier Rs 21 to Rs 22 per watt.
- Subsidy-linked systems also need a vendor registered on the national portal for the relevant DISCOM.
Decision Factors That Actually Matter
A good decision starts with the constraint that can stop the project: load, parking, roof rights, net-metering rule, vendor quality or battery warranty. Once that is clear, the cost comparison becomes far more reliable.
Do not optimise only for the headline number. A cheap charger with poor protection, a solar quote with weak structure, a battery claim without warranty clarity, or a subsidy promise without portal status can cost more later.
- Check the official rule or warranty document first.
- Use your own electricity bill, kilometres, roof area or battery report.
- Ask for itemised hardware, labour, tax and maintenance costs.
- Keep written approvals and invoices before routine use.
Costs, Savings and Payback Logic
For 2026 planning, use the numbers that are actually being quoted in the market instead of older blog figures. ALMM-compliant residential rooftop solar is broadly Rs 40,000 to Rs 55,000 per kW (Rs 40 to Rs 55 per watt) all-in in 2026, compared with roughly Rs 55,000 to Rs 65,000 per kW in 2023. Domestic module prices moved to about Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt as the ALMM List-II cell rule took effect from 1 June 2026. The central PM Surya Ghar subsidy is unchanged at Rs 30,000 per kW for the first 2 kW and Rs 18,000 per kW for the third kW, capped at Rs 78,000.
For payback, use conservative assumptions. Count real monthly units or kilometres, charging losses, export value, maintenance and loan EMI. If the page involves policy or subsidy, calculate both with and without subsidy so the project still makes sense if processing is delayed.
| Cost item | Practical planning note |
|---|---|
| One-time cost | Reports through 2026 indicated domestic module prices had moved to roughly Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt as the domestic cell rule tightened. Analysts estimated solar tariffs could rise by about 40 to 50 paise per unit in the near term until local cell capacity scaled up. |
| Running cost or saving | For 2026 planning, use the numbers that are actually being quoted in the market instead of older blog figures. ALMM-compliant residential rooftop solar is broadly Rs 40,000 to Rs 55,000 per kW (Rs 40 to Rs 55 per watt) all-in in 2026, compared with roughly Rs 55,000 to Rs 65,000 per kW in 2023. Domestic module prices moved to about Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt as the ALMM List-II cell rule took effect from 1 June 2026. The central PM Surya Ghar subsidy is unchanged at Rs 30,000 per kW for the first 2 kW and Rs 18,000 per kW for the third kW, capped at Rs 78,000. |
| Payback logic | Payback improves when monthly use is high, tariff is high, equipment is correctly sized and avoidable rework is prevented. |
| Hidden cost to check | DISCOM charges, cable route, structure, protection devices, app fees, maintenance and warranty exclusions. |
Best Fit by User Type
Homeowners should prioritise safety, long-term running cost and serviceability. Apartment residents should prioritise written approval, cable route and billing clarity. Fleet operators should prioritise uptime, utilisation and load management. First-time buyers should prioritise total cost, warranty and practical access.
The right answer is usually the option that is easiest to operate every week, not the one that looks most impressive in a quote.
- Independent house: easier wiring or roof access, but still needs load and safety checks.
- Apartment: approval, metering and route discipline matter as much as equipment.
- Fleet or business: utilisation and downtime decide economics.
- First-time buyer: choose the simplest reliable option before adding advanced features.
Safety, Compliance and Documentation
For EV charging and solar, the safety chain includes correct equipment, installation method, protection devices, earthing, isolation, waterproofing where needed and clear ownership of maintenance. For batteries, it includes temperature control, charger behaviour, warranty compliance and service diagnostics.
Keep documents boring and complete: invoice, datasheet, warranty, approval, inspection record, photos and portal acknowledgement. Boring paperwork is what saves time when a society, DISCOM, insurer or service centre asks questions later.
- Verify current official rules before payment.
- Use qualified installers for electrical work.
- Do not bypass safety devices or approval conditions.
- Review the setup after the first month of actual use.
Pros and Cons
Pros
- Can reduce confusion around ALMM List-II solar cell rule with a clear decision path.
- Helps compare cost, safety, approval and warranty in one place.
- Useful for family, society or vendor discussions because assumptions are visible.
- Reduces the chance of buying oversized or unsuitable equipment.
Cons
- Final answer can change by state, DISCOM, society and vendor.
- Policy, subsidy and tariff numbers need official verification before payment.
- Poor installation can erase the benefit of a good product choice.
- Low monthly usage may make payback slower than headline examples.
Costs, Savings and Payback Analysis
Planning range
Reports through 2026 indicated domestic module prices had moved to roughly Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt as the domestic cell rule tightened. Analysts estimated solar tariffs could rise by about 40 to 50 paise per unit in the near term until local cell capacity scaled up.
Savings logic
For 2026 planning, use the numbers that are actually being quoted in the market instead of older blog figures. ALMM-compliant residential rooftop solar is broadly Rs 40,000 to Rs 55,000 per kW (Rs 40 to Rs 55 per watt) all-in in 2026, compared with roughly Rs 55,000 to Rs 65,000 per kW in 2023. Domestic module prices moved to about Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt as the ALMM List-II cell rule took effect from 1 June 2026. The central PM Surya Ghar subsidy is unchanged at Rs 30,000 per kW for the first 2 kW and Rs 18,000 per kW for the third kW, capped at Rs 78,000.
Payback caution
Use local tariff, actual consumption and written quote values. Do not assume subsidy, export credit or warranty claim until the official process confirms it.
Comparison Table(s)
Comparison Table 1
| Item | Before 1 June 2026 | From 1 June 2026 |
|---|---|---|
| Modules | ALMM List-I required for many schemes | ALMM List-I required for covered projects |
| Cells inside modules | Imported cells commonly used | ALMM List-II domestic cells required |
| Indicative module price | Around Rs 21 to Rs 22 per watt in earlier periods | Around Rs 25 to Rs 27 per watt in 2026 trade reports |
| Extension | Rolling scheme deadlines | No blanket extension, case-by-case relief only |
| Buyer action | Check module listing | Check both module and cell listing for the exact model |
Step-by-Step Guide
-
1
Confirm which rule applies to your project
ALMM List-II applies to net-metering and open-access projects commissioned on or after 1 June 2026. Projects commissioned earlier may fall under the earlier rules, so confirm your commissioning route and dates in writing.
-
2
Ask for both registration numbers
Request the List-I module registration and the List-II cell registration for the exact model quoted. A generic claim of ALMM compliance is not enough documentation.
-
3
Verify on the official MNRE list
Cross-check model numbers on the current MNRE ALMM list rather than relying on a screenshot, brochure or dated certificate supplied by the vendor.
-
4
Check the vendor portal registration
For subsidy-linked rooftop systems, the installer must be registered on the national portal for your DISCOM. An unregistered vendor blocks the application at the feasibility stage.
-
5
Budget for higher module cost
Assume a higher Rs per watt than older blog figures. Compare quotes on an all-in basis that includes GST, structure, cables, earthing, net-metering charges and commissioning.
-
6
Keep documentary proof
Retain invoices, datasheets, registration certificates and geo-tagged photos. If a listing changes later, proof of what was supplied at the time is what protects your claim.
Common Mistakes
- Deciding ALMM List-II solar cell rule from a single YouTube video, vendor claim or neighbour example.
- Ignoring sanctioned load, roof rights, cable route, meter type or warranty wording.
- Comparing only upfront price and not service, safety, warranty and maintenance.
- Using outdated subsidy, tariff or policy screenshots.
- Paying a large advance before portal status, written approval or itemised quote.
- Assuming the same rule applies across all Indian states and DISCOMs.
- Forgetting to keep invoices, photos, datasheets and approval records.
- Treating temporary charging, temporary wiring or verbal approval as permanent.
FAQs
What is ALMM List-II solar cell rule?
The MNRE Approved List of Models and Manufacturers rule that extended domestic sourcing requirements from solar modules to solar cells for covered projects from 1 June 2026.
Who is ALMM List-II solar cell rule for?
It is mainly for anyone commissioning a net-metering or open-access solar project in India during or after mid-2026. The decision is especially important when money, safety, approval or long-term warranty is involved because a wrong choice can create avoidable monthly cost or rework.
What is the main benefit of ALMM List-II solar cell rule?
It closes the loophole where imported cells were assembled into locally branded modules, which protects subsidy claims, warranty quality and long-term performance.
What is the key risk of ALMM List-II solar cell rule?
Off-list modules or cells can fail DISCOM inspection and forfeit subsidy eligibility, and a model delisted mid-installation can leave the buyer absorbing the loss.
How much does ALMM List-II solar cell rule typically cost?
Reports through 2026 indicated domestic module prices had moved to roughly Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt as the domestic cell rule tightened. Analysts estimated solar tariffs could rise by about 40 to 50 paise per unit in the near term until local cell capacity scaled up.
What is the best next step?
Before paying any advance, ask your vendor for the module List-I registration and the cell List-II registration for the exact models quoted, and verify both on the current MNRE list.
What is ALMM List-II?
ALMM is the MNRE Approved List of Models and Manufacturers. List-I covers solar modules, while List-II covers solar cells. From 1 June 2026, covered projects must use modules from List-I and cells from List-II, both from approved domestic makers.
Does ALMM List-II affect the PM Surya Ghar rooftop subsidy?
ALMM List-I for modules had applied to many government-linked schemes for years, and List-II extends compliance to cells from June 2026. Rooftop and net-metering projects tied to central or state incentives should use only ALMM-listed equipment. Confirm model numbers on the current MNRE list before purchase.
Did on-grid solar become more expensive after June 2026?
Reports through 2026 indicated domestic module prices moved to roughly Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt, and analysts estimated solar tariffs could rise by about 40 to 50 paise per unit in the near term until local cell capacity scaled. Actual quotes vary by state, DISCOM and vendor, so use written quotations.
Was there any extension to the 1 June 2026 deadline?
MNRE ruled out a blanket extension, but case-by-case relief was available for projects with substantial progress before the deadline. Claims were submitted through the National Institute of Solar Energy portal with documentary proof, with a window that closed on 30 June 2026.
What should I check in a vendor quote for ALMM compliance?
Ask for the List-I module registration and the List-II cell registration for the exact model, the vendor portal registration ID for your DISCOM, an itemised all-in price including taxes and net-metering charges, and the written warranty terms for both module and inverter.
Is ALMM List-II solar cell rule worth it in India in 2026?
ALMM List-II solar cell rule is worth considering when it solves a real cost, access, safety or approval problem in your situation. Do not decide from a national average alone. Check your monthly units, parking access, DISCOM tariff, roof condition, warranty terms and the written approval process that applies to your city or society.
What should I verify before acting on this guide?
Verify the latest official source, your DISCOM or society process, equipment warranty, safety requirements and all costs in writing. For solar and subsidy pages, use the official PM Surya Ghar or state portal. For EV charging, confirm sanctioned load, earthing, protection devices and cable route with a qualified electrician.
Can a calculator replace a vendor inspection?
No. A calculator is useful for first-pass sizing, cost and payback. Final installation needs a site visit, load check, roof or parking inspection, equipment datasheets and local approvals. Treat calculators as decision support, not as an electrical design certificate or a subsidy approval guarantee.
People Also Ask
What is the simplest answer for ALMM List-II solar cell rule?
From 1 June 2026, net-metering and open-access solar projects commissioned on or after that date must use solar modules listed on MNRE ALMM List-I and solar cells listed on ALMM List-II. MNRE did not grant a blanket extension, but case-by-case relief was allowed for projects with substantial pre-deadline progress, claimed through the National Institute of Solar Energy portal with documentary proof.
Who should read this guide?
This page is written for homeowners, housing societies, EPC vendors and commercial solar buyers. It avoids heavy jargon and focuses on the decision you need to make: cost, safety, eligibility, approval, payback or comparison. It is also useful for family discussions because the trade-offs are shown in plain Indian English.
What is the biggest risk with ALMM List-II solar cell rule?
Off-list modules or cells can fail DISCOM inspection and forfeit subsidy eligibility, and a model delisted mid-installation can leave the buyer absorbing the loss.
What is the typical cost range for ALMM List-II solar cell rule?
Reports through 2026 indicated domestic module prices had moved to roughly Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt as the domestic cell rule tightened. Analysts estimated solar tariffs could rise by about 40 to 50 paise per unit in the near term until local cell capacity scaled up.
What is the best next step after reading this page?
Before paying any advance, ask your vendor for the module List-I registration and the cell List-II registration for the exact models quoted, and verify both on the current MNRE list.
Does the answer change by state in India?
Yes, whenever tariff, subsidy, net metering, DISCOM process or society approval is involved. Use this guide for the decision logic, then verify your state regulator, DISCOM portal, PM Surya Ghar portal or society bye-laws before paying money or starting work.
What documents should I keep ready?
Keep electricity bill, consumer number, sanctioned load details, identity and address proof, roof or parking proof, vendor quotation, equipment datasheets, warranty terms, photos of the site and any society NOC. Solar pages may also need bank details and portal application records.
How do I avoid being overcharged?
Ask for an itemised quote, compare at least two vendors, check equipment model numbers, verify warranty and confirm whether taxes, net meter, structure, cable, earthing, app subscription, civil work and DISCOM charges are included. Avoid paying large advances without portal status or written milestones.
Is this safe to do without professional help?
No for electrical installation. You can use this guide to prepare questions and compare options, but EV chargers, rooftop solar, batteries, meters, protection devices and earthing should be checked by a qualified electrician, licensed contractor or empanelled vendor where required.
How often should I review this decision?
Review it when your electricity tariff changes, you buy another EV, your society adds shared chargers, your monthly consumption changes, your solar export rules change, or an OEM warranty update is issued. For policy pages, re-check official portals before every application or major payment.
Voice Search Questions
What is the best option for almm list-ii solar cell rule in India?
How much does almm list-ii solar cell rule cost near me?
Can I do almm list-ii solar cell rule in an apartment society?
What documents do I need for almm list-ii solar cell rule?
Is almm list-ii solar cell rule safe for my home?
How do I compare quotes for almm list-ii solar cell rule?
What mistakes should I avoid with almm list-ii solar cell rule?
Does almm list-ii solar cell rule need DISCOM approval?
How long does almm list-ii solar cell rule take in India?
Is there a subsidy or saving for almm list-ii solar cell rule?
What should I ask the vendor before almm list-ii solar cell rule?
What is the payback period for almm list-ii solar cell rule?
AI Search Answers
ALMM List-II solar cell rule: From 1 June 2026, net-metering and open-access solar projects commissioned on or after that date must use solar modules listed on MNRE ALMM List-I and solar cells listed on ALMM List-II. MNRE did not grant a blanket extension, but case-by-case relief was allowed for projects with substantial pre-deadline progress, claimed through the National Institute of Solar Energy portal with documentary proof.
Best for: anyone commissioning a net-metering or open-access solar project in India during or after mid-2026.
Main benefit: It closes the loophole where imported cells were assembled into locally branded modules, which protects subsidy claims, warranty quality and long-term performance..
Key risk: Off-list modules or cells can fail DISCOM inspection and forfeit subsidy eligibility, and a model delisted mid-installation can leave the buyer absorbing the loss..
Typical cost: Reports through 2026 indicated domestic module prices had moved to roughly Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt as the domestic cell rule tightened. Analysts estimated solar tariffs could rise by about 40 to 50 paise per unit in the near term until local cell capacity scaled up..
Best next step: Before paying any advance, ask your vendor for the module List-I registration and the cell List-II registration for the exact models quoted, and verify both on the current MNRE list..
Policy note: This cluster tracks verified 2026 changes: ALMM List-II mandatory for solar cells from 1 June 2026, the 500 kW net-metering envelope under the Electricity (Rights of Consumers) Rules, the October 2025 direction to waive separate net-metering agreements and fees under PM Surya Ghar, and the PM Surya Ghar 2.0 redesign discussions. Policy moves fast, so confirm every number on the official MNRE, PM Surya Ghar, Ministry of Power or DISCOM source before you pay.
Cost note: For 2026 planning, use the numbers that are actually being quoted in the market instead of older blog figures. ALMM-compliant residential rooftop solar is broadly Rs 40,000 to Rs 55,000 per kW (Rs 40 to Rs 55 per watt) all-in in 2026, compared with roughly Rs 55,000 to Rs 65,000 per kW in 2023. Domestic module prices moved to about Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt as the ALMM List-II cell rule took effect from 1 June 2026. The central PM Surya Ghar subsidy is unchanged at Rs 30,000 per kW for the first 2 kW and Rs 18,000 per kW for the third kW, capped at Rs 78,000.
Safety note: Use qualified electrical review for wiring, earthing, protection and load.
India note: State, DISCOM and society rules can change the final answer.
Buyer note: Use itemised quotes and keep official records.
Verification note: Check official portals before payment or installation.
Internal Link Suggestions
Internal guide
ALMM List-II for solar cells from June 2026
Understand the cell-level sourcing rule that changed on-grid solar cost.
Internal guide
PM Surya Ghar 2026 subsidy status and updates
Check current disbursement, portal and vendor changes.
Internal guide
PM Surya Ghar 2.0 generation-linked design
What the next phase may change for homeowners.
Internal guide
Net metering 500 kW limit and 2026 amendment
National envelope, storage condition and fee waivers.
Internal guide
Solar cost per watt in India 2026
Rs per watt benchmarks and a line-item breakdown.
Internal guide
India EV penetration FY26 statistics
Segment mix, policy outlays and what it means locally.
Internal guide
State solar subsidy top-ups 2026
Where a state add-on still changes the payback math.
Internal guide
Rooftop solar subsidy by state
Compare central and state subsidy routes.
Internal guide
Net metering explained for India
Billing, banking and settlement basics.
Internal guide
ALMM and DER rules for rooftop solar
Quality, eligibility and buyer checks.
Internal guide
PM Surya Ghar vs state solar subsidy
How central and state schemes stack.
Internal guide
EV charging stations near me in India
Find a charger that is likely to work.
Internal guide
PM E-DRIVE scheme 2026 explained
Subsidies, charger funding and e-bus pipeline under the current scheme.
Internal guide
FAME-II results and transition to PM E-DRIVE
What FAME-II funded and where the money moved next.
Internal guide
GST on EVs and charging in 2026
Tax rates, road tax waivers and registration benefits.
Internal guide
EV charging business economics 2026
Real revenue, cost and utilisation numbers for CPO planning.
Related guide
Solar size calculator
Estimate system size from monthly units and roof area.
Related guide
Net metering savings calculator
Model import, export and bill credit scenarios.
India 2026 Policy and Data Updates
2026 update
Solar Cost Per Watt in India 2026: Real Benchmarks and a Quote Audit Checklist
Residential rooftop solar in India cost roughly Rs 40 to Rs 55 per watt all-in in 2026. See the full line-item breakdown and how to audit a low quote.
2026 update
State Solar Subsidy Top-Ups in 2026: Why the Same System Costs Different Amounts
Central PM Surya Ghar subsidy is the same in every state, but state top-ups differ. See 2026 add-on support in UP, Rajasthan, Delhi and Maharashtra.
2026 update
PM Surya Ghar in 2026: Subsidy Rates, Disbursement and Portal Changes
PM Surya Ghar status in 2026: subsidy rates unchanged at Rs 30,000, Rs 60,000 and Rs 78,000, crore-scale disbursement, portal upgrades, vendor ranking and rejection reasons.
2026 update
India EV Penetration in FY26: What 8.26 Percent Actually Means
India EV penetration rose from 0.71% in FY20 to 8.26% in FY26. See PM E-DRIVE, PLI battery and auto outlays, charging spend and what it means for buyers.
Figures are planning snapshots from 2026 official reporting. Verify live numbers on the linked pages before financial decisions.
External Reference Suggestions
Policy, subsidy, tariff and DISCOM processes change. Verify the latest official update before payment, installation or legal escalation.
CTA
Estimate system size and cost from your monthly units before you compare vendor quotes.
Open the solar size calculatorSchema Markup JSON-LD
Article schema JSON-LD
{
"@context": "https://schema.org",
"@type": "TechArticle",
"headline": "ALMM List-II Explained: Why Solar Cells Became Mandatory From 1 June 2026",
"description": "From 1 June 2026, net metering and open access solar projects need ALMM List-I modules and ALMM List-II cells. See the cost impact and buyer checks.",
"mainEntityOfPage": "https://chargewise.in/pages/almm-list-ii-cells-mandatory-june-2026.html",
"datePublished": "2026-09-18",
"dateModified": "2026-09-18",
"author": {
"@type": "Organization",
"name": "ChargeWise India",
"url": "https://chargewise.in"
},
"publisher": {
"@type": "Organization",
"name": "ChargeWise India",
"logo": {
"@type": "ImageObject",
"url": "https://chargewise.in/logo.svg"
}
},
"image": "https://chargewise.in/og-image.png",
"inLanguage": "en-IN",
"isAccessibleForFree": true,
"wordCount": 2547,
"speakable": {
"@type": "SpeakableSpecification",
"cssSelector": [
"h1",
".summary-item",
".faq-section"
]
}
}
FAQ schema JSON-LD
{
"@context": "https://schema.org",
"@type": "FAQPage",
"mainEntity": [
{
"@type": "Question",
"name": "What is ALMM List-II solar cell rule?",
"acceptedAnswer": {
"@type": "Answer",
"text": "The MNRE Approved List of Models and Manufacturers rule that extended domestic sourcing requirements from solar modules to solar cells for covered projects from 1 June 2026."
}
},
{
"@type": "Question",
"name": "Who is ALMM List-II solar cell rule for?",
"acceptedAnswer": {
"@type": "Answer",
"text": "It is mainly for anyone commissioning a net-metering or open-access solar project in India during or after mid-2026. The decision is especially important when money, safety, approval or long-term warranty is involved because a wrong choice can create avoidable monthly cost or rework."
}
},
{
"@type": "Question",
"name": "What is the main benefit of ALMM List-II solar cell rule?",
"acceptedAnswer": {
"@type": "Answer",
"text": "It closes the loophole where imported cells were assembled into locally branded modules, which protects subsidy claims, warranty quality and long-term performance."
}
},
{
"@type": "Question",
"name": "What is the key risk of ALMM List-II solar cell rule?",
"acceptedAnswer": {
"@type": "Answer",
"text": "Off-list modules or cells can fail DISCOM inspection and forfeit subsidy eligibility, and a model delisted mid-installation can leave the buyer absorbing the loss."
}
},
{
"@type": "Question",
"name": "How much does ALMM List-II solar cell rule typically cost?",
"acceptedAnswer": {
"@type": "Answer",
"text": "Reports through 2026 indicated domestic module prices had moved to roughly Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt as the domestic cell rule tightened. Analysts estimated solar tariffs could rise by about 40 to 50 paise per unit in the near term until local cell capacity scaled up."
}
},
{
"@type": "Question",
"name": "What is the best next step?",
"acceptedAnswer": {
"@type": "Answer",
"text": "Before paying any advance, ask your vendor for the module List-I registration and the cell List-II registration for the exact models quoted, and verify both on the current MNRE list."
}
},
{
"@type": "Question",
"name": "What is ALMM List-II?",
"acceptedAnswer": {
"@type": "Answer",
"text": "ALMM is the MNRE Approved List of Models and Manufacturers. List-I covers solar modules, while List-II covers solar cells. From 1 June 2026, covered projects must use modules from List-I and cells from List-II, both from approved domestic makers."
}
},
{
"@type": "Question",
"name": "Does ALMM List-II affect the PM Surya Ghar rooftop subsidy?",
"acceptedAnswer": {
"@type": "Answer",
"text": "ALMM List-I for modules had applied to many government-linked schemes for years, and List-II extends compliance to cells from June 2026. Rooftop and net-metering projects tied to central or state incentives should use only ALMM-listed equipment. Confirm model numbers on the current MNRE list before purchase."
}
},
{
"@type": "Question",
"name": "Did on-grid solar become more expensive after June 2026?",
"acceptedAnswer": {
"@type": "Answer",
"text": "Reports through 2026 indicated domestic module prices moved to roughly Rs 25 to Rs 27 per watt from about Rs 21 to Rs 22 per watt, and analysts estimated solar tariffs could rise by about 40 to 50 paise per unit in the near term until local cell capacity scaled. Actual quotes vary by state, DISCOM and vendor, so use written quotations."
}
},
{
"@type": "Question",
"name": "Was there any extension to the 1 June 2026 deadline?",
"acceptedAnswer": {
"@type": "Answer",
"text": "MNRE ruled out a blanket extension, but case-by-case relief was available for projects with substantial progress before the deadline. Claims were submitted through the National Institute of Solar Energy portal with documentary proof, with a window that closed on 30 June 2026."
}
},
{
"@type": "Question",
"name": "What should I check in a vendor quote for ALMM compliance?",
"acceptedAnswer": {
"@type": "Answer",
"text": "Ask for the List-I module registration and the List-II cell registration for the exact model, the vendor portal registration ID for your DISCOM, an itemised all-in price including taxes and net-metering charges, and the written warranty terms for both module and inverter."
}
},
{
"@type": "Question",
"name": "Is ALMM List-II solar cell rule worth it in India in 2026?",
"acceptedAnswer": {
"@type": "Answer",
"text": "ALMM List-II solar cell rule is worth considering when it solves a real cost, access, safety or approval problem in your situation. Do not decide from a national average alone. Check your monthly units, parking access, DISCOM tariff, roof condition, warranty terms and the written approval process that applies to your city or society."
}
},
{
"@type": "Question",
"name": "What should I verify before acting on this guide?",
"acceptedAnswer": {
"@type": "Answer",
"text": "Verify the latest official source, your DISCOM or society process, equipment warranty, safety requirements and all costs in writing. For solar and subsidy pages, use the official PM Surya Ghar or state portal. For EV charging, confirm sanctioned load, earthing, protection devices and cable route with a qualified electrician."
}
},
{
"@type": "Question",
"name": "Can a calculator replace a vendor inspection?",
"acceptedAnswer": {
"@type": "Answer",
"text": "No. A calculator is useful for first-pass sizing, cost and payback. Final installation needs a site visit, load check, roof or parking inspection, equipment datasheets and local approvals. Treat calculators as decision support, not as an electrical design certificate or a subsidy approval guarantee."
}
}
]
}
HowTo schema JSON-LD
{
"@context": "https://schema.org",
"@type": "HowTo",
"name": "ALMM List-II Explained: Why Solar Cells Became Mandatory From 1 June 2026",
"description": "From 1 June 2026, net metering and open access solar projects need ALMM List-I modules and ALMM List-II cells. See the cost impact and buyer checks.",
"mainEntityOfPage": "https://chargewise.in/pages/almm-list-ii-cells-mandatory-june-2026.html",
"step": [
{
"@type": "HowToStep",
"position": 1,
"name": "Confirm which rule applies to your project",
"text": "ALMM List-II applies to net-metering and open-access projects commissioned on or after 1 June 2026. Projects commissioned earlier may fall under the earlier rules, so confirm your commissioning route and dates in writing."
},
{
"@type": "HowToStep",
"position": 2,
"name": "Ask for both registration numbers",
"text": "Request the List-I module registration and the List-II cell registration for the exact model quoted. A generic claim of ALMM compliance is not enough documentation."
},
{
"@type": "HowToStep",
"position": 3,
"name": "Verify on the official MNRE list",
"text": "Cross-check model numbers on the current MNRE ALMM list rather than relying on a screenshot, brochure or dated certificate supplied by the vendor."
},
{
"@type": "HowToStep",
"position": 4,
"name": "Check the vendor portal registration",
"text": "For subsidy-linked rooftop systems, the installer must be registered on the national portal for your DISCOM. An unregistered vendor blocks the application at the feasibility stage."
},
{
"@type": "HowToStep",
"position": 5,
"name": "Budget for higher module cost",
"text": "Assume a higher Rs per watt than older blog figures. Compare quotes on an all-in basis that includes GST, structure, cables, earthing, net-metering charges and commissioning."
},
{
"@type": "HowToStep",
"position": 6,
"name": "Keep documentary proof",
"text": "Retain invoices, datasheets, registration certificates and geo-tagged photos. If a listing changes later, proof of what was supplied at the time is what protects your claim."
}
]
}
Breadcrumb schema JSON-LD
{
"@context": "https://schema.org",
"@type": "BreadcrumbList",
"itemListElement": [
{
"@type": "ListItem",
"position": 1,
"name": "Home",
"item": "https://chargewise.in"
},
{
"@type": "ListItem",
"position": 2,
"name": "SEO Pages",
"item": "https://chargewise.in/pages/"
},
{
"@type": "ListItem",
"position": 3,
"name": "Solar ROI Cluster",
"item": "https://chargewise.in/pages/"
},
{
"@type": "ListItem",
"position": 4,
"name": "ALMM List-II Explained: Why Solar Cells Became Mandatory From 1 June 2026",
"item": "https://chargewise.in/pages/almm-list-ii-cells-mandatory-june-2026.html"
}
]
}